Monticello Dam is a 304-foot (93Â m) high concrete arch dam in Napa County, California, United States constructed between 1953 and 1957. The dam impounded Putah Creek to create Lake Berryessa in the Vaca Mountains.
Lake Berryessa is currently the seventh largest man-made lake in California. Water from the reservoir primarily supplies agriculture in the Sacramento Valley downstream. The dam is noted for its classic, uncontrolled morning-glory type spillway. The diameter at the lip is 72Â ft (22Â m). Locally, the spillway is also known as 'The Glory Hole'.
To the south is Putah Creek State Wildlife Area.
StatisticsEdit
Although the dam and its 26-mile (42Â km) long reservoir are located entirely in eastern Napa County, the dam lies less than 500Â ft (150Â m) west of the boundary with Yolo County. In addition, parts of the lake's watershed extend into Lake County.
Monticello is a concrete medium thick arch dam 304Â ft (93Â m) high from the foundations, 1,023Â ft (312Â m) long and 239Â ft (73Â m) above the riverbed. The dam is 100Â ft (30Â m) thick at the base, tapering to 12Â ft (3.7Â m) at the crest. The total volume of construction materials is 326,000 cubic yards (249,000Â m3).
The capacity of the reservoir is 1,602,000 acre·ft (1.976Ã109 m3), with a full surface area of 20,700 acres (8,400 ha). The maximum operating elevation is 440 ft (130 m); any higher water levels will flow over the dam's spillway. About 375,000 acre feet (0.463 km3) of runoff flow into the reservoir each year from its 566-square-mile (1,470 km2) watershed.
The Monticello Dam Powerplant was completed in 1983 and has three generators, totaling a capacity of 11.5 megawatts (MW). The powerplant is operated and maintained by the Solano Irrigation District. The electrical power is sent mostly to the North Bay area of San Francisco.
As of 1992, about 71,445 acres (28,913Â ha), or nearly 75Â percent, of the project command area was irrigated. Water is diverted 6 miles (9.7Â km) downstream of Monticello at the Putah Diversion Dam, and distributed to farms through the 33-mile (53Â km) Putah South Canal. The canal ends at Terminal Reservoir, which supplies water to the city of Vallejo. A 1999 contract provides for the delivery of 207,350 acre feet (0.25576Â km3) of water each year for irrigation. About 32,000 acre feet (0.039Â km3) of municipal water are also supplied by the project.
Since construction the dam and reservoir have prevented about $5,015,000 in flooding related damages.
HistoryEdit
The dam was built as part of the Solano Project, which was intended to provide a full irrigation supply to 96,000 acres (39,000 ha) of prime agricultural bottomland in Solano County and Yolo County. The project lands have been farmed since the 1840s, but irrigation was difficult due to the lack of a reliable summer water supply. The Berryessa Valley, where the dam and reservoir are located today, was formerly part of Rancho Las Putas, 35,500-acre (14,400 ha) 1843 land grant to José and Sixto Berryessa, for whom the area is named. By the 1860s the rancho had been subdivided into many smaller parcels; before damming, the valley was one of California's most fertile agricultural regions, centering on the town of Monticello, with roughly 250 residents.
The Solano Project first took shape in the 1940s after the formation of the Solano Irrigation District to manage the water resources of Putah Creek. On November 11, 1948 the Secretary of the Interior formally authorized the project, which would be constructed by the Bureau of Reclamation. The Bureau initially intended to incorporate the project as part of its larger Central Valley Project (CVP), which would manage the combined watersheds of the Sacramento and San Joaquin rivers. However, locals strongly favored that Solano be financed and operated separately from the CVP. A Senate hearing in 1953 confirmed that Solano would be constructed as an independent project.
Land purchases in the future reservoir area were made in early 1953; however, landowners were allowed to stay throughout the construction period until their property was actually flooded by rising lake levels. The inhabitants of Berryessa Valley vehemently opposed the project, as did the city of Winters (one of the would-be beneficiaries of the project) because of close social ties to the town of Monticello. Opponents of the big dam proposed that a series of smaller reservoirs be constructed to supply the water, but this was deemed uneconomical. Most of Monticello's residents moved out by summer 1956, as rising waters approached the town. After the area was vacated, crews deforested the valley and demolished the existing buildings and infrastructure. About 300 graves had to be relocated to higher ground.
The primary construction contract was awarded to a consortium formed by Peter Kiewit Sons Co. and Parish Brothers, for construction of the main dam and relocation of California State Route 128, which ran through the Berryessa Valley. Excavation of the dam site and construction of a diversion tunnel continued through 1954, with the first concrete placed on August 9, 1955. Despite major flooding between January and May 1956, more than 90Â percent of the concrete had been laid by December 1956, and the dam was topped out on November 7, 1957, at a total cost of about $37 million. This figure also includes the cost for associated downstream irrigation works and the highway relocation.
The reservoir took five years to fill after construction, reaching capacity for the first time on April 18, 1963. The reservoir completely inundated Monticello (though the city's ruins are visible at low water levels), and flooded 20,700 acres (8,400Â ha) of the surrounding Berryessa Valley. At the time, Lake Berryessa was the second-largest volume reservoir in California, after Shasta.
The reservoir has become a popular summer recreation area, attracting as many as 1.3 million visitors each year. The Bureau of Reclamation operates five recreational areas around the lake, providing boat ramps and day use facilities. Recreational use has been declining since 2012, due to budget problems that have forced the closure of local resorts. This has also caused economic collapse of the surrounding area, causing many residents to move away.
SpillwayEdit
The dam's morning glory type spillway, known as the Glory Hole, is 72 feet (22Â m) in diameter at lake level and narrows down to about 28 feet (8.5Â m) at the exit. At the lake's peak level the spillway can drain 48,400 cubic feet per second (1,370Â m3/s), which occurs when the lake level rises to 15.5 feet (4.7Â m) above the level of the funnel.
Water spills over its lip when the lake reaches 1,602,000 acre feet (1.976Ã109Â m3) and a reservoir elevation of 440 feet (130Â m) above sea level. The last time the reservoir naturally spilled through the glory hole was on the afternoon of February 16, 2017.
After a number of storms had caused the lake level to rise 35.5 inches since January 1, 2017, the reservoir is now on the cusp of spilling once again at 439.2 feet. Eager to witness this event, a number of local boaters and recreation enthusiasts generated enough wake to cause the reservoir to spill, albeit briefly, at 1:45pm on February 13, 2017. Lake Berryessa reservoir filled and ran into its glory hole spillway for the first time in over a decade on February 16, 2017 at approximately 3:00 PM PST .
Current lake level status is available at Solano County Water Agency.
Swimming near the Glory Hole is prohibited. In 1997, Emily Schwalek of Davis died after being caught in the current while swimming near the Glory Hole and being swept down the pipe after holding on to the rim for about 20 minutes.
See alsoEdit
- List of dams and reservoirs in California
- List of the tallest dams in the United States